Wankabori Thermal Power Station

Plant CategoryState Generator
Total Installed Capacity1,470 MW
Fuel CategoryThermal
Fuel TypeCoal
DistrictKheda
StateGujarat
StatusOperational
Group CompanyGujarat Urja Vikas Nigam Ltd.
Websitewww.gseb.com
Cleaning Water SourceMahi River

Unit Detail

S.No Phase Unit Installed Capacity Commissioning Date Fuel Status
1 - 1 210.00 23-Mar-1982 Coal Operational
2 - 2 210.00 15-Jan-1983 Coal Operational
3 - 3 210.00 15-Mar-1984 Coal Operational
4 - 4 210.00 03-Sep-1986 Coal Operational
5 - 5 210.00 23-Sep-1986 Coal Operational
6 - 6 210.00 18-Nov-1987 Coal Operational
7 - 7 210.00 31-Dec-1998 Coal Operational

Gujarat Urja Vikas Nigam Ltd.Power plants of this group company!!

S.No Generator Capacity Category State Fuel Status
1 Gandhinagar Thermal Power Station 870 State Gujarat Coal Operational
2 Sikka Thermal Power Station 240 State Gujarat Coal Operational
3 Dhuvaran Gas Based Combined Cycle Power Plant-II 107 State Gujarat Gas Operational
4 Dhuvaran Gas Based Combined Cycle Power Plant-I 112 State Gujarat Gas Operational
5 Kutch Lignite Thermal Power Station 290 State Gujarat Coal Operational
6 Akrimota Lignite Power Plant 250 State Gujarat Coal Operational
7 Sardar Sarovar-Canal Head Power House 250 State Gujarat Hydro Operational
8 Sardar Sarovar-River Bed Power House 1200 State Gujarat Hydro Operational
9 Kadana Pump Storage Power Plant 240 State Gujarat Hydro Operational
10 Utran Gas Based Combined Cycle Power Plant-I 135 State Gujarat Gas Operational
11 Utran Gas Based CCPP -II 375 State Gujarat Gas Operational
12 Ukai Thermal Power Station 1350 State Gujarat Coal Operational
13 Ukai Hydro Power Station 300 State Gujarat Hydro Operational
14 Ukai LBC Hydro Power Station 5 State Gujarat Hydro Operational
15 Pipavav CCPP 703 State Gujarat Gas Operational
16 Dhuvaran CCPP Exp 376 State Gujarat Gas Operational