CERC fixes transmission charges for assets associated with projects in the western region

  • Economic Times, ET Bureau / Hyderabad
  • Created: Wed 15th APR 2015

The Central Electricity Regulatory Commission (CERC) has approved the transmission tariff for Power Grid Corporation of India Limited’s (Powergrid) transmission assets covered under the scheme for transmission system strengthening associated with independent power producers’ generation projects in Chhattisgarh in the western region.

The approved and claimed annual transmission charges are summarised in the table below:

CERC-approved annual transmission charges for Powergrid’s transmission systems (Rs million)

Asset

COD

2014-15 (Pro-rata)

2015-16

Claimed charges

Approved charges

Claimed charges

Approved charges

Asset-I: 765 kV D/C Wardha-Aurangabad transmission line  and associated bays along with a 765 kV, 3X80 MVAR line reactor at the Aurangabad substation

July 8, 2014

                    1,577.44

                         1,110.26

                    2,240.81

                         1,577.16

Asset-II: 765/400 kV, 1,500 MVA ICT-1 with bays and equipment at the Aurangabad substation

July 1, 2014

                        100.10

                               72.50

                        151.06

                            109.41

Asset-III: 400 kV, 80 MVAR switchable line reactor for the Aurangabad-Boiser transmission line ckt-1 charged as bus reactor at the Aurangabad substation

October 2, 2014

                          11.55

                                 9.24

                          24.68

                               19.75

Asset-IV: 400 kV, 80 MVAR switchable line reactor for the Aurangabad-Boiser transmission line ckt-2 charged as bus reactor at the Aurangabad substation

October 1, 2014

                          11.44

                                 8.51

                          24.29

                               18.07

Asset-V: 765/400 kV, 500 MVA ICT-3 with bays and equipment at Boiser

January 2, 2015

                          16.03

                               10.09

                          68.98

                               43.43

Asset-VI: 400 kV, 80 MVAR line reactor for the Aurangabad-Boiser transmission line ckt-1 charged as bus reactor at the Boiser substation

January 11, 2015

                            5.96

                                 4.46

                          25.80

                               19.29

Asset-VII: 400 kV, 80 MVAR line reactor for the Aurangabad-Boiser transmission line ckt-I charged as bus reactor at the Boiser substation

January 7, 2015

                            4.95

                                 3.70

                          21.06

                               15.73

D/C: double circuit; ckt: circuit; ICT: interconnecting transformer; COD: Commercial operation date

Source: CERC

 

The charges allowed in the order will be applicable from the date of commercial operation of transmission assets. Further, the CERC has directed Powergrid to submit additional information such as trial operation certificate and details of time overrun.

Tags

Western Region Power Grid Independent Power Producers Grid Transmission System Central Electricity Regulatory Commission Tariff Electricity Regulatory Commission PowerGrid transmission charges Power Electricity India

Related News

  • Adani Power, Azure Power win solar projects bids in Uttar Pradesh  Read more
  • Adani Power Maharashtra gets a lot of relief from MERC  Read more
  • French power major EDF plans $2 billion green bet on India  Read more
  • Domestic firms take lead in solar park tender in Karnataka  Read more
  • Power Finance Corp Q3 net marginally up at Rs 1,117 cr  Read more
  • Government has equal focus on all renewable power sources: Piyush Goyal  Read more
  • 35 open access companies return to Maharashtra power discom's fold  Read more
  • Discoms asked to present green energy report  Read more
  • Power generation exceeds target by almost 6 per cent in April: Central Electricity Authority  Read more
  • SC dismisses PNGRB's plea on fixing price of natural gas  Read more