Jaitapur Nuclear Power Plant: French firm EDF wants larger role in building 6 reactors, submits fresh proposal

  • Economic Times, ET Bureau / Hyderabad
  • Created: Mon 17th JUL 2017

 

A French firm, which is to build six atomic reactors at Jaitapur, has submitted a fresh plan to the NPCIL proposing to share a larger role in the engineering aspect of the project, a top executive of the company said.  The firm, EDF, and the NPCIL have also resolved to sign the General Framework Agreement (GFA) for the Jaitapur Nuclear Power Plant (JNPP) by the end of the year.

French President Emmanuel Macron is likely to visit India by the year-end and the two sides are working to fast track the negotiations so that the GFA could be signed during that time, the EDF official, who did not wish to be quoted, said.  An EDF delegation also meet officials of the Prime Minister’s Office and the Ministry of External Affairs to discuss the issue.

The EDF is to build six reactors, each with a capacity of 1650 MW each. When operational, the proposed plant, some 500 km south of Mumbai, will be the largest nuclear power generation park in the country. A construction of a nuclear plant is usually discussed in terms of the EPC (Engineering, Procurement and Construction).

The EDF has proposed to take care of the engineering part and a large chunk of the procurement of equipment which have to be sourced from abroad, the official said. This position has been different from what Areva, which has been taken over by EDF, had proposed when the negotiations had initially begun.

However, the EDF insists that the Nuclear Power Corporation of India (NPCIL) should take care of the construction part as it has an experience of building the Kudankulam Nuclear Power Plant (KKNPP).

The NPCIL, on the other hand, wants the EDF to take the full responsibility of the EPC, citing the reason that the EPR technology is new to India.  A senior Indian government official, on condition of anonymity, pointed out that the GFA hinges on three aspects — lower tariff, credit and a functional reference plant. No call has been taken on the fresh proposal given by the NPCIL, the official said.

“Discussions are on between the Ministry of Finance and the French Treasury Department to resolve the issues related to credit. Some part of it will be in euros while the rest will be in rupees,” the EDF official said.  The Flamanville EPR nuclear power reactor, which has been shown as a reference plant for the JNPP, is expected to be commissioned by 2018, the French official hoped.

The EDF is constructing another EPR plant at Taishan in Guangdong province of China and it is expected to be operational by the end of this year, the official added.

Tags

Nuclear Power Corporation of India Ltd Finance Power Generation Tariff China Power Plant Nuclear Power Mumbai Power India Kudankulam Nuclear Power Plant

Related News

  • Over 30 distressed power projects on block, big companies uninterested  Read more
  • Power ministry special secretary may get RECs charge too  Read more
  • Govt to up cap on subsidised LPG to nine  Read more
  • Bhakra Beas Management Board beat CEA's power generation target for 2015-16  Read more
  • Competition Commission rejects complaint against Tata Power  Read more
  • UDAY could help pare discom losses but bringing them down to zero might prove elusive  Read more
  • NHAI eyes LPG bottling plant to expand highway  Read more
  • Kudgi power plant in Karnataka to be commissioned in 2017: Government  Read more
  • Lanco says power plant to shut down if gas supplies dwindle  Read more
  • Suzlon Energy bags order to set up 90 mw wind energy project for ReNew Energy  Read more